  1. Dig a 50 x 50 cm wide and approx. 30 cm deep pit. Important: Do not enter the pit to avoid compression!
  2. Cover the soil with a gravel layer to prevent soil flotation. Insert a measuring rod into the ground. 10 cm above the pit bottom place a mark on the measuring rod.
  3. Now fill the pit with water and replenish for 1-2 hours regularly (e.g. garden hose).
  4. Fill water up to the mark. After 10 minutes, fill as much water as necessary to raise the water level back to the mark using a measuring bucket. The soil permeability can be estimated from the quantity of refilled water.
  5. Repeat step 4 as many times (at least 3 times), until a consistent value is established.

Evaluation: Water quantity < 1.5 litres in 10 minutes: little infiltration possible (silt)
Water quantity = 1.5 litres in 10 minutes: infiltration possible (silty sand)
Water quantity > 3 litres in 10 minutes: good infiltration possible (sand, gravel)